Highway 604:02 – Rural Highway Improvements
Alberta Transportation
East of Gull Lake to west of Morningside

In 2007, Al-Terra was retained by Alberta Transportation to provide preliminary design, right of way acquisition, detailed design, tender preparation, and construction management to rebuild almost 17 km of Highway 604 from Highway 761 to Highway 2A. This section of highway is currently a gravel-surfaced road, with significant truck traffic from local gravel pits. Maintenance costs, dust control, and overall public safety are the primary drivers for this highway project.

The first contract from Range Road 272 to Highway 2A is currently under construction. The detailed design for the second contract is expected to be complete in the spring of 2013. Construction to finish the upgrades to Highway 792 will start once funding becomes available.